Overview

Development Timeline

Our development process involved a lot of trial and error, as well as research. We took advice from industry experts and our teacher advisor to further our progress throughout the process.

Moon Image

Development Statistics

9
Meetings
1
Presentation
12
Iterations
46
Days

Our Timeline

We phased out a timeline to help us manage our project. This ensured that we would be on track to finish the challenge on time. Each step represents a week.

  • 1

    Week 1 โ€“ Oct 9th thru Oct 15th

    Review Development Guide, view sample app videos, view last years winngers, LVC 1 Event

  • 2

    Week 2 โ€“ Oct 16th thru Oct 22nd

    Research coding platform, research landing site, team name, Haworth Site paper, LVC 2 Event

  • 3

    Week 3 โ€“ Oct 23rd thru Oct 29th

    Finalize Region, create documentation, 3d mesh and visualization, landing sites

  • 4

    Week 4 โ€“ Oct 30th thru Nov 5th

    Finalize landing site, visualize height/slope/elevation, path finding algorithm

  • 5

    Week 5 โ€“ Nov 6th thru Nov 12th

    Community engagement, begin website development

  • 6

    Week 6 โ€“ Nov 13th thru Nov 20th

    Finalize desitation site, visualize minimap on 3d mesh, toggle features, LVC 3 Event

  • 7

    Week 6 โ€“ Nov 14th thru Nov 21th

    Finalize project and publish website